Tunnelling below trains
Did you know?
🚂The Werrington Grade Separation project: purpose and design
- The £240 million Werrington Grade Separation project will increase capacity on the East Coast Main Line
- The 155-metre-long tunnel is the world’s longest single underground jacked structure and weighs more than the Eiffel Tower
- The new structure should be virtually maintenance-free for its 120-year design life
Jacked box tunnels are nothing new, as a method of creating an opening beneath a busy road or railway with minimal disturbance. A jacked structure is constructed, normally in reinforced concrete and usually rectangular in shape, adjacent to where it will be located, and then thrust forward horizontally into place using high-capacity hydraulic jacks, while the ground is excavated in front. This allows the road or railway to continue operating overhead or during a very short closure. This method becomes impractical for large or long tunnels since the friction forces become too much for the jacks, and jacking around curves creates an extra order of complexity.
The challenge at Werrington near Peterborough was to replace a flat crossing by diverting a freight line beneath the East Coast Main Line (ECML) at a very acute angle. The Werrington Grade Separation project is part of Network Rail’s £1.2 billion upgrade of the ECML and is being built by Morgan Sindall Infrastructure under a design-and-construct contract, with Mott Macdonald as design partner. Tony Gee & Partners is sub-consultant for the jacked tunnel elements, with additional advice from UK company Jacked Structures, whose founder James Thomson is patent holder for the system adopted.
The challenge at Werrington near Peterborough was to replace a flat crossing by diverting a freight line beneath the East Coast Main Line (ECML) at a very acute angle
The team decided on a system that involved replacing the conventional box section of the jacked tunnel with a portal – just the two side walls and the roof – and leaving the floor to be cast in situ once the jack was complete. This reduced the weight of the structure and, more importantly, removed the primary source of friction during the slide: between the base of the box and the ground.
Why a dive-under at Werrington?
🚞The factors that influenced the decision of a jacked portal at Werrington
At Werrington, freight trains from the east (Spalding, Lincoln and beyond) have to join and cross the busy East Coast Main Line (ECML) to connect to the Stamford line that runs parallel to the ECML to the west. Each crossing can block the line for up to 10 minutes, so separating the junction will allow more frequent mainline services, with improved capacity.
A fly-over would have created an eyesore visible for miles around in the flat landscape, would also have had to cross two roads and would have required a costly relocation of high-voltage power cables. A shorter tunnel at a less acute angle would have required a wide sweep of new track for which land was not available. Network Rail’s original plan was a ‘jigsaw’ solution of small connecting sections of tunnel created by sheet-piling and roofing over, each built in a short but disruptive closure of the ECML, with each closure running the risk of over-run if anything went wrong. The curve could have been avoided by jacking a straight structure, but this would have had to be exceptionally wide to accommodate the necessary curvature of the track inside. The ECML could have been carried on three temporary truss bridges while the excavation was carried out underneath, but due to the skew, the bridges would have had to be very long, with massive foundations.
A bored tunnel (or twin tunnels) would have had to be much deeper, with more extensive approach works and additional risk as the site is in a flood plain. A jacked box while keeping the ECML open throughout would have been challenging at such an acute angle and would also have been several metres deeper than the solution adopted, with longer approaches.
Hence, a jacked portal provided the best solution, with most construction off-line, just one short track closure, and minimal risk of unplanned disruption to the ECML. As a single structure, with no joints or bearings, it should also be virtually maintenance-free for its 120-year design life.
Creating the portal
This could only be done if there was a firm foundation for the walls of the portal to slide on. Engineers at Morgan Sindall Infrastructure achieved this by first driving two small-diameter tunnels under the railway, precisely on the alignment of the portal foundations. These were then half-filled with reinforced concrete to provide a smooth surface for the portal to slide on, with side walls cast in to help guide the portal round the bend, and they then later act as permanent foundations for the structure.
The chosen layout required a 155 m-long tunnel, 9.5 m wide and 5.1 m high with 1 m-thick walls, on a curve of 750 m constant radius. Preparatory works included diverting a river and various services, relocating some of the existing freight track to make space for the new works, and excavating the approach ramps.
Last August, engineers used an earth pressure balance tunnel boring machine to drive the two curved guide tunnels. This type of machine is used in soft ground, and uses the excavated earth to support the tunnel face as it is excavated. Each of the 3.5 m diameter guide tunnels were lined with ‘permanent’ concrete segments to ensure no settlement of the ECML overhead before the main structure was jacked. Cages of reinforcing bar were inserted inside the tunnels, and the guide path was concreted in.
The giant concrete portal – weighing more than the Eiffel Tower at 11,000 t – was constructed on the eastern approach, over a reaction slab that included 34 rows of sunken ‘pockets’ as well as slide path beams on each side linking to those in the guide tunnels. The reaction slab provided a foundation to construct the portal. Cast pockets in the reaction slab accommodated relocatable reaction frames for the jacks to push against. At the rear of the portal, large moveable steel reaction frames were lowered to engage in the pockets and provide something for the jacks to push against, for each stage of the push: every 5.4 m the reaction frames were lifted and relocated in the next pocket. The four large jacks together had a capacity of 5000 t, bearing on a thrust slab – a short 10 m-long section of the eventual tunnel floor between the feet of the portal.
Testing the jacking system
The jacking itself was originally targeted for a track possession in September 2020, but the first COVID-19 lockdown put paid to an already very tight programme. Network Rail had a full complement of works for December, and instead provided a nine-day track possession in January 2021– although a skeleton Main Line service was maintained throughout, by diverting passenger trains to one of the realigned freight tracks.
In December, a short 13.5 m trial push was successfully completed, to test the jacking system before the portal reached the ECML. From soon after midnight on 16 January, the ECML track over the tunnel was lifted together with ballast and topsoil to expose the stiff clay beneath. Then the jacking could commence, with the clay removed by hydraulic excavators operating both within the front of the box and from the surface above. Cutters were fixed to the front walls of the portal, to trim the cut to just 50 mm outside the portal walls.
As the drive progressed, the top sections of the guide tunnels’ segmental linings were removed to open up the new guide track. Low-friction PTFE (commonly known as Teflon) pads were fixed to the guide track at regular intervals to provide a smooth-running surface: the portal ran over the pads on a series of 28 steel skidding beams, each attached to the underside of the portal walls and activated by two lift jacks.
Overcoming additional challenges
Getting round the bend was an additional challenge, as this had only been attempted once before (in the Netherlands) and that was for a much smaller tunnel. The ‘steering’ came from a hydraulically linked lateral guidance system: a series of 40 jacks located in slots in the bottom of the portal walls maintaining sideways pressure on the sides of the guide paths.
Resistance to the thrust was expected to have three components: friction of the portal walls’ skidding beams running on the slide paths with their PTFE pads; front loads from the cutting edges of the portal walls pushing against the soil ahead; and side friction as the unsupported soil slumped against the walls. The resistance was expected to increase as the tunnel progressed. As it turned out, the front load during jacking was less than expected, and there was no side friction at all: the excavators and side cutters were able to trim the ground accurately, and the unsupported vertical sides of the clay held up well, leaving just a 50 mm-wide gap. The peak thrust required was only 900 t, and two of the four jacks proved redundant.
Steering too went like clockwork. A constant pressure was exerted by the lateral jacks on each side, and this proved sufficient to steer the structure round the bend with very little adjustment.
Avoiding the delay of crossing freight trains will allow the frequency of ECML high-speed services to be increased from six to eight per hour
The only difficulty came with the PTFE pads, which occasionally buckled and needed to be replaced more frequently than expected, causing minor delays. Even so, working 24 hours a day in three shifts, the jack was completed, the portal lowered on to its permanent foundations, the 50 mm gap between the wall and the clay was backfilled with pea gravel and then grouted from inside with cementitious grout through holes in the walls to minimise any future settlement, and the ballast and track re-laid overhead – all comfortably within the nine-day window. The track was handed back to Network Rail with 52 minutes to spare.
With plenty of finishing work to complete, the first freight trains are expected to use the new tunnel in November. Avoiding the delay of crossing freight trains will allow the frequency of ECML high-speed services to be increased from six to eight per hour, but passengers will not see this benefit until May 2022 when the new timetable is introduced – by which time passenger numbers on long-distance high-speed trains may well have risen back to pre-COVID-19 numbers.
The £240 million Werrington Grade Separation project is part of Network Rail’s much larger ECML upgrade, a large part of which is renewing track, signalling and overhead line equipment at London’s King’s Cross station and its approaches.
***
This article has been adapted from "Tunnelling below trains", which originally appeared in the print edition of Ingenia 87 (June 2021).
Contributors
Hugh Ferguson
Author
John Agar was key in supporting and helping to develop and lead the design solution developed for the Werrington Grade Separation project. An experienced engineer, John has worked within the industry for several years.
Andy Robinson is a specialist tunnelling engineer with over 30 years’ practical, design and management experience in jacked installations on the worldwide stage.
Pieter Esbach has a wealth of experience in leading and delivering complex multi-million pound civil engineering schemes. Committed to driving innovation and working collaboratively, Pieter played an integral role in leading the safe delivery of the Werrington Grade Separation project.
Keep up-to-date with Ingenia for free
SubscribeRelated content
Mechanical
When will cars drive themselves?
There are many claims made about the progress of autonomous vehicles and their imminent arrival on UK roads. What progress has been made and how have measures that have already been implemented increased automation?
R&D investment makes good business sense
In just five years, Dr Ralf Speth FREng has presided over a revolution in design and manufacturing that has helped create a new family of engines and has overhauled Jaguar Land Rover (JLR) production facilities.
Bikes help improve skills and attitude
The Archway Project is an independently-funded scheme that is expanding its engineering-based programmes by providing BTEC certificates and diplomas. John Milton, the director of the project, explains what the charity does to help reduce anti-social behaviour and improve employment prospects.
High speed evolution
In December 2010, Eurostar International Ltd awarded a contract for 10 new high speed trains to Siemens. The company has used a system developed over decades to maximise the performance and passenger-carrying ability of its 320km/h trains.
Other content from Ingenia
Quick read
- Environment & sustainability
- Opinion
A young engineer’s perspective on the good, the bad and the ugly of COP27
- Environment & sustainability
- Issue 95
How do we pay for net zero technologies?
Quick read
- Transport
- Mechanical
- How I got here
Electrifying trains and STEMAZING outreach
- Civil & structural
- Environment & sustainability
- Issue 95